You signed in with another tab or window. Reload to refresh your session.You signed out in another tab or window. Reload to refresh your session.You switched accounts on another tab or window. Reload to refresh your session.Dismiss alert
As per our Sprint Planning Meeting, and as the Product Owner, you have agreed to the following Product Backlog Items (PBIs) being included in the current sprint backlog.
The Team will do its best to deliver this set of features (Scope), to a defined quality standard (Definition of Done) by the end of the sprint. Ideally the team will deliver what they forecast, or even a bit more, but this can't be guaranteed.
Title
URL
Assignees
Status
Estimate
Sprint
💄 Mobile | Update quiz results page (requires designer review)
To: Adam, Seth
Cc: Matt G., Zach, Anton
(Checked by Matt G)
Hi Seth,
Sprint Goals (in priority order):
Please see below for a more detailed breakdown of the upcoming Sprint:
As per our Sprint Planning Meeting, and as the Product Owner, you have agreed to the following Product Backlog Items (PBIs) being included in the current sprint backlog.
The Team will do its best to deliver this set of features (Scope), to a defined quality standard (Definition of Done) by the end of the sprint. Ideally the team will deliver what they forecast, or even a bit more, but this can't be guaranteed.
https://github.com/orgs/SSWConsulting/projects/7/views/15?filterQuery=sprint:@next
<This is as per rule: https://www.ssw.com.au/rules/sprint-forecast />
The text was updated successfully, but these errors were encountered: