Issue:
When the 1st of the month is on a Saturday and a job recurrence schedule indicates the 2nd, 3rd, 4th or 5th weeks of the month, the starting month will not calculate correctly.
Steps to reproduce:
Create a Volunteer Campaign
Create a Volunteer Job attached to that Campaign
Create a Job Recurrence Schedule for that Volunteer Job and choose the following:
Day of the Week: Saturday
Weekly Occurrence: 2nd
Scheduled Start Date & Time: 01/08/2022 5:00 PM
Duration: 2
Click Save
Notice that the Shifts created are 2/12, 3/12 and 4/9 but not 1/8.
Workaround
As a workaround, either manually create the missing or incorrectly dated Volunteer Shifts or choose the 1st day of the Month as the Start Date/Time.
The text was updated successfully, but these errors were encountered:
Issue:
When the 1st of the month is on a Saturday and a job recurrence schedule indicates the 2nd, 3rd, 4th or 5th weeks of the month, the starting month will not calculate correctly.
Steps to reproduce:
Workaround
As a workaround, either manually create the missing or incorrectly dated Volunteer Shifts or choose the 1st day of the Month as the Start Date/Time.
The text was updated successfully, but these errors were encountered: