- Start Time
- Finish Time
- Profit or Value Associated
Input: Number of Jobs n = 4
Job Details {Start Time, Finish Time, Profit}
Job 1: {1, 2, 50}
Job 2: {3, 5, 20}
Job 3: {6, 19, 100}
Job 4: {2, 100, 200}
Output: The maximum profit is 250.
We can get the maximum profit by scheduling jobs 1 and 4.
Note that there is longer schedules possible Jobs 1, 2 and 3
but the profit with this schedule is 20+50+100 which is less than 250.